Brazil’s proposal to tax super-rich globally finds many takers in G20 GroupCPM manifesto promising annihilation of all weapons of mass destructions including nuclear, draws flak from Defence MinisterBiden favours higher steel tariff on ‘cheating’ China + may up tariff on dominant solar tech suppliersUS Poll: Biden trumps Trump in money race by USD 75 mnNetanyahu says Israel to decide how and when to respond to Iran’s aggressionGoogle slays costs by laying off staffers & shifting roles outside USCoast Guard apprehends Indian fishing boat with unauthorised cashI-T - Sales supported by payments through banking channel which were not only disclosed in VAT returns but duly verified & accepted by VAT Department, cannot be treated as bogus to invoke Sec 68: ITATSPACE, testing & evaluation hub for sonar systems, set up by DRDO, inaugurated in KeralaGST - Malabar 'Parota' Is Akin To 'Bread', Exigible To 5% GST: HCST - Principles of constructive res judicata applies - Petitioner cannot seek to assail proceedings on grounds which were available to be raised in first round of litigation: HCHeavy downpours drown Dubai; Airport issues travel advisoryGST - If the Proper Officer was of the view that any further details were required, the same could have been specifically sought before passing any order - Matter remitted: HCHM pledges to make India completely Maoist-freeGST - Proper Officer has not applied his mind to the reply submitted and has merely held it to be devoid of merits - Order set aside and matter remitted: HCGST - Order was issued without hearing the petitioner - It is just and necessary to provide an opportunity to petitioner to contest the tax demand on merits: HCGST - Classification - It is incumbent on the respondent to duly consider all contentions raised by petitioner objectively without any pre-determination: HCGST - Whether the amount reflected as ITC tallies with the value of credit notes issued - Petitioner's explanation not duly examined - Matter remanded: HCGST Penalty of Rs. 3731 Crores on an employee!CCI okays acquisition of additional shareholding of Thyssenkrupp by Protos EngineeringMicrosoft to inject USD 1.5 bn in AI Group G42 of UAEDRDO organises workshop on 'Emerging Technologies & Challenges for Exoskeleton'Canadian budget proposes more taxes on higher income groups & tax credits for EVsI-T - Since application filed for condonation of delay is rejected by order without stating reason is set aside and application is restored for reconsideration: HCWorld leaders appeal for quick ratification of UN Ocean TreatyI-T- Re-assessment - if assessee submits objections thereto, then AO must pass order dealing with objections & also establish that facts presented by assessee are prima facie incorrect: HCUK House debates ban on smokingI-T- Deduction u/s 43B in respect of GST cannot be disallowed, where assessee is found to have paid GST before due date of filing ITR: ITATGlobal economy to grow at 3.2% in current year and also 2025: IMFGreat Barrier Reef in Australia suffers serious bleachingVAT - Input Credit - mere production of invoices or payment made by cheques/RTGS is enough to discharge burden of proof upon assessee: HCUS to impose fresh sanctions on Iran’s missile programmeDelhi Police nabs woman for thieving luxury SUVs
 
Rural connectivity by all-weather roads: Govt prepones target year by three years

By TIOL News Service

 

NEW DELHI, NOV 24, 2015: THE Government has brought forward the target date by three years from 2022 to 2019 to achieve complete rural connectivity through all-weather roads under Pradhan Mantri Gram Sadak Yojana, PMGSY. Union Minister for Rural Development Birender Singh said that this accelerated implementation will be achieved by providing enhanced financial allocation and through a modified funding pattern in the Scheme. He said, the government has also decided to increase the annual allocation during year 2015-16 by Rs. 5,000 crore and with this the total Central allocation to States would be Rs. 15,100 crore, while it was Rs 9,960 crore during 2014-15. It may be noted that the Central release to the States for PMGSY works was Rs.5, 196 crore in 2013-14 and Rs. 4,313 crore in 2012-13.

PMGSY was launched in year 2000 as a Centrally Sponsored Scheme with the objective to provide single all-weather road connectivity to all eligible unconnected rural habitations. Under PMGSY-I, 1,78,184 unconnected habitations were identified. However, in 15 years of implementation so far, 1,12,550 habitations (63%) have been connected with PMGSY roads. The States are yet to complete the roads to provide connectivity to about 37% of habitations as per the mandate of the Scheme.

Mr Singh said that higher allocation of funds will ensure that Scheme targets are achieved by March, 2019 much before the stipulated time of 2022. He said, this decision of the government will give a big boost for public investment in the rural sector particularly rural infrastructure.

The Minister said that his Ministry is also considering to financially incentivise the States who achieve the targets allocated to them, within the prescribed time frame. This incentive could be used for periodic maintenance expenditure by the States. He said, the Ministry of Rural Development is working in collaboration with the States for preparing a time bound action plan to cover the outstanding liabilities for sanctioned works so as to meet the liabilities of all sanctioned works within 2016-17. The Minister said, the enhanced level of Central allocation to States for 2015-16 as well as the proposed allocation of the same amount for 2016-17 would help in providing connectivity to 29,000 eligible habitations in these two years which would be much higher than 13,424 habitations connected during 2012-13 and 2013-14.

The Minister also informed that consequent to higher devolution of funds to the States as per the recommendations of 14th Finance Commission, the Sub-Group of Chief Ministers on Rationalization of Centrally Sponsored Schemes was constituted and it has submitted its Report wherein it has recommended that fund sharing pattern of PMGSY will be in the ratio of 60:40 between the Centre and States for all States except for 8 North Eastern and 3 Himalayan States for which it will be 90:10. He said, the Sub-Group has also recommended that this modified sharing pattern should be effective from Financial Year 2015-16 onwards. The above recommendation of the Sub-Group on modified sharing pattern has been accepted and all ongoing as well as outstanding works would be covered under this sharing pattern.


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.




Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.